image1.jpg image2.jpg image3.png
Information Sheet of Rice Related Project/Program in CARD First Group Countries
1. Country Ghana
2. Title (Full name) Project for Promotion of Farmers' Patricipation in Irrigation Management (FAPIM)
3. Project Location 22 irrigated agriculture sites developed by GIDA
4. Type of project 3
1. Grant, 2. Loan, 3. Technical Coop./Assistance, 4. National budget, 5. Private sector
5. Field of support 3 7 10
1. Policy, 2. R & D, 3. Extension & Training, 4. Production, 5. Marketing
6. Post-harvest, 7. Irrigation, 8. Credit, 9. Seed, 10. Other ( specify below )
10. Capacity building
6. Fund sources
(Funding agency)
JICA
7. Budget Japanese yen 250 million
8. Project duration Start: October, 2004
(dd/mm/yy) End: September, 2006
9. Goal and objectives Goal: Income increase of irrigated agriculture in the GIDA irrigation project sites and the improvement of farmer participatory irrigation system management
Obj.: To establish the base for farmer participatory irrigation sysytem management depending on the legal system and mutual agreements in the GIDA irrigation project sites.
To strengthen the service of GIDA on irrigated agriculture technology.
10. Target beneficiaries Direct: Staff of GIDA
Sec.:
11. Project component (activities) 1. Establishment of legal system for farmer participation in irrigation system management
2. Development of implemention structure for the irrigation facility management between GIDA and farmers
3. Improvement of capacity of GIDA staff for planning and implementation of the training on irrigated agriculture technology
12. Expected results (outputs) 1. Legal system to promote farmer participation in irrigation sysytem management is establised.
2. Implemention structure for the irrigation facility management is developed between GIDA and farmers.
3. Capacity of GIDA staff for planning and implementation of the training on irrigated agriculture technology is improved.
13. Inputs 1. Exprets (Long-term and Short-term)
2. Training of GIDA staff in Japan
3. Neccessary machinery and equipment
4. Agreed operational costs of the Project
14. Implementing agency GIDA
15. Status of the project 4 1. Pipeline, 2. Approved, 3. On-going, 4. Completed
16. Issues/problems
Key Word: